5CE5 QUANTITY SURVEYING & VALUATION |
|
|
|
L 3 |
|
|
|
Unit: 1 |
|
Purpose and importance of estimates, principles of estimating. Methods |
|
Introduction: |
|
of taking out quantities of items of work. Mode of measurement, measurement sheet |
|
and abstract sheet; bill of quantities. Types of estimate, plinth area rate, cubical content |
|
rate, preliminary, original, revised and supplementary estimates for different projects. |
|
|
|
Unit: 2 |
|
Task for average artisan, various factors involved in the rate of an item, |
|
Rate Analysis: |
|
material and labor requirement for various trades; preparation for rates of important |
|
items of work. Current schedule of rates. (C.S.R.) |
|
|
|
Unit: 3 |
|
Preparing detailed estimates of various types of buildings, R.C.C. works, |
|
Estimates: |
|
earth work calculations for roads and estimating of culverts Services for building such |
|
as water supply, drainage and electrification. |
|
|
|
Unit: 4 |
|
Factors affecting cost of work, overhead charges, Contingencies and |
|
Cost of Works: |
|
work charge establishment, various percentages for different services in building. |
|
|
|
Unit: 5 |
|
Valuation: |
|
Purposes, depreciation, sinking fund, scrap value, year’s purchase, gross |
|
and net income, dual rate interest, methods of valuation, rent fixation of buildings |